Concrete calculator

A 10 × 10 ft, 4 in slab needs 1.36 yd³ of concrete with 10% extra, or 62 bags of 80 lb mix.

Concrete to order
1.36 yd³ [3]
80 lb bags
62 [1]
Ready-mix truckloads
1 [3]
Units
Shape
Slab: what to measureA drawing of the shape marking the length, width, and thickness.LengthWidthThicknessSide view of the slab4 in of concrete with no gravel base.Concrete 4 in
Common slab sizes
ft
ft

4 in (10 cm) is typical for patios and walkways.

in

The ready-mix industry recommends 4% to 10% extra for spills and uneven ground.

%
Gravel base (optional)
Gravel base (optional)

The compacted layer of gravel or crushed stone under the concrete. Leave the depth empty for no base.

The depth once compacted.

in

Gravel shrinks 20% or more when compacted (FHWA).

%
$per ton
Material cost (optional)
Material cost (optional)

Enter your local prices to see what the order costs. Prices vary by area and supplier.

Bag size you are pricing

Delivered, from your local supplier.

$per yd³
$

Concrete to order

1.36 yd³

1.23 yd³ for the shape, plus 10% extra.

Concrete to order. 1.36 yd³. 1.23 yd³ for the shape, plus 10% extra.

What to buy
Cubic yards1.36
Cubic feet36.67
80 lb bags62
60 lb bags82
40 lb bags123
Ready-mix truckloads1

How it's calculated

A slab, wall or footing is a box: length × width (or height) × thickness. A round slab or column is π × radius² × its thickness or height. Solid steps on the ground are stacked blocks: the bottom step is one block tall, the next two, and so on, so n steps hold n × (n + 1) ÷ 2 blocks of width × rise × run.

Curb and gutter is its cross-section times its length. The curb is a block as deep as the curb and as tall as the curb height plus the gutter's thickness, and the gutter is a flat slab beside it: curb depth × (curb height + gutter thickness) + gutter width × gutter thickness.

Volumes are worked out in cubic feet and converted exactly: 27 cubic feet make a cubic yard, and a foot is 0.3048 m.

Bags are rounded up to whole bags of the order volume. An 80 lb bag of concrete mix makes about 0.60 cubic feet, a 60 lb bag 0.45 and a 40 lb bag 0.30.

Ready-mix trucks carry 8 to 12 cubic yards, so the truckload count is a range. Most suppliers also have a minimum order, so check before ordering a small amount.

A gravel base covers the area the concrete sits on (length × width, a round slab's or column's circle, a wall's length × thickness, the steps' width × total run, or the curb and gutter's length × its full width) to the compacted depth you choose, plus extra loose gravel for compaction: most gravels shrink at least 20% when compacted. Its weight uses 105 lb per cubic foot for dry gravel.

The material cost uses the prices you enter: the order volume × your ready-mix price, or the whole bags needed × your price per bag. There are no built-in prices, because they vary too much by area and supplier.

Sources

  1. QUIKRETE Concrete Mix No. 1101 product data sheet, Quikrete International (2022-10)
  2. Sakrete High-Strength Concrete Mix technical data sheet, Sakrete (Oldcastle APG) (2023)
  3. CIP 31: Ordering Ready Mixed Concrete, National Ready Mixed Concrete Association (2023)
  4. PCC Truck Mixer (citing AASHTO), Pavement Interactive (2026)
  5. NIST Handbook 44, Appendix C: General Tables of Units of Measurement, National Institute of Standards and Technology (2026)
  6. Dirt and Mud Densities (gravel, dry: 105 lb/ft³), The Engineering ToolBox (2026)
  7. Caterpillar Performance Handbook, Edition 50: Weight of Materials (loose density), Caterpillar Inc. (June 2022)
  8. Gravel Roads: Maintenance and Design Manual (compaction shrinks gravel 20% or more), U.S. Federal Highway Administration (November 2000)
  9. International Residential Code 2024, R404.1 foundation walls (6, 8, 10 and 12 in nominal) and R506.1 slabs (3½ in minimum), International Code Council (via UpCodes) (2024)
  10. Residential Structural Design Guide, Chapter 4: foundation walls are typically 6, 8 or 10 in thick, U.S. Department of Housing and Urban Development (NAHB Research Center) (2000)
  11. Pre-Delivery Instructions: a reinforced concrete pad at least 4 in thick, Hot Spring Spas (Watkins Manufacturing) (2017)
  12. Picking the Right Hot Tub Foundation: at least 4 in thick, 6 in for swim spas, Bullfrog Spas (November 2023)
  13. Standard Plan A87A, Curbs and Driveways (Type A2-6: 0.05903 yd³ per linear foot), California Department of Transportation (2024)
  14. Standard Plate 7100H, Concrete Curb and Gutter Design B (B624: 0.0690 yd³ per linear foot), Minnesota Department of Transportation (2005)
  15. Highway Standard 606001-08, Combination Concrete Curb and Gutter (B-6.24), Illinois Department of Transportation (January 2022)

Last reviewed October 5, 2026.